top of page

Building Our Vermicomposting Toilet System: An Off-Grid IBC Blackwater Setup

When we started rebuilding our granite stone house in Portugal, I knew one thing before we poured the floor slab: I did not want all our wastewater disappearing down the same pipe.


So we separated it.


The toilet wastewater, or blackwater, received its own pipework. Water from the showers, sinks, washing machine, dishwasher, and kitchen went to a separate greywater system. Both routes were planned before the concrete floor was poured, because changing your mind about buried drainage pipes after several tonnes of concrete are sitting on top of them is what engineers politely call poor planning.


That left me with another question. What should I actually do with the blackwater?


I looked at several options before deciding to build a Vermicomposting Toilet System based largely on the IBC vermifilter and greenfilter concept described by VermicompostingToilets.net. Their approach uses an aerobic filter bed containing composting worms and organic material. Solids remain within the vermifilter while liquid drains through the media and continues to a downstream treatment area. Vermifiltration itself has also been studied as a form of wastewater treatment in both small-scale and full-scale systems.


What follows is not a universal construction specification. It is the story of how I built ours, using the site, materials, pipe fittings, organic matter, and tools available to me here in Central Portugal.


And there is another important detail.


The system is built, and the worms are already living inside it, but our renovated house is not yet connected to its final well-water pumping and filtration system. That means the toilet system is not yet receiving normal daily use.


I had to start somewhere to eventually finish somewhere.


Once we have a full year of real use behind us, I plan to come back with the much more interesting question: How did it actually perform?


For now, keep reading to see exactly how I built it. At the end, Herman's Tough Kraut Fixes covers some of the construction questions I had to solve along the way.


Why We Separated Blackwater Before Pouring the Floor


A large part of this project was decided long before the first worm entered the IBC.


During the granite house renovation, we installed separate wastewater routes inside the new floor construction and cast the pipes into the concrete slab. The blackwater line serves only the toilet. Everything else goes into our separate greywater system.


Grey drainage pipes and upright vents are laid across black membrane beneath steel reinforcement mesh before the slab is poured.
Separate blackwater and greywater pipework laid into the granite-house floor before the concrete slab was poured.

That separation was deliberate.


Our greywater contains water from the showers, hand basins, washing machine, dishwasher, and kitchen sink. The toilet produces a very different waste stream, so I wanted the option to manage it separately instead of designing one system around everything coming from the house.


For the blackwater route, I continued with 125 mm PVC drainage pipe from the house.

The site helped me considerably. The vermicomposting IBC sits more than 2 m (6.6 ft) lower than the wastewater outlet from the house, which allowed me to design the entire route around gravity rather than pumps.


I laid the 125 mm pipe at a fall of at least 2 degrees. Instead of using one sharp change in direction, I used pairs of 45-degree fittings to create gentler bends. At the tank, another two 45-degree pieces direct the pipe down through the existing central opening in the top of the IBC.


The result is simple. Toilet wastewater travels downhill from the house and drops directly onto the organic filter material inside the tank.


That passive gravity-fed idea was one of the things that attracted me to this type of system in the first place. The IBC-based design I followed is intended to work without mechanical processing equipment when the site provides enough gravity fall.


Our normal household load will also be small. The house is intended primarily for two people, rather than a large family or commercial property.


Tough Tip: If you are still at the stage where your floor is open, think about wastewater before concrete arrives. Separating our pipes during construction gave me options that would have been far harder to create later.


Interior of an IBC tank showing a vertical mesh-wrapped filter pipe connected to grey and black plumbing near the tank floor.
The drainage assembly installed inside the empty IBC before adding gravel, mesh, or organic material.

Building Our Vermicomposting Toilet System From an IBC Tank


The heart of our build is wonderfully unglamorous: a standard 1,000 L (264 gal) IBC tank.


I cut open part of the upper section to provide access, following the general layout of the IBC design that inspired the project. The tank remains accessible from above because this is a biological system I expect to inspect, observe, and eventually maintain rather than bury and forget.


IBC tank with grey inlet pipe beside a wheelbarrow of gravel and a shovel, set into a rocky trench for an off-grid toilet system.
Gravel ready for the base layer of our 1,000 L IBC vermifilter, with the blackwater inlet already routed into the tank.
Herman Kraut holds a grey perforated pipe fitting attached to a mesh-wrapped filter tube, with the IBC tank and gravel behind.
Small drainage holes added to the lower fitting help liquid enter the protected outlet assembly beneath the filter bed.

Filter assembly parts arranged on gravel, including a long mesh-covered perforated tube, grey connectors, elbow, and black pipe.
The perforated drainage assembly before installation, wrapped in plastic mesh to help keep coarse material away from the outlet.

Creating the drainage layer


I began inside the empty tank. At the bottom, I installed the vertical drainage pipe and wrapped it with a non-rusting plastic mesh. I then filled the bottom of the IBC with roughly 10–15 cm (4–6 in) of gravel, bringing the gravel level up to the drainage arrangement.


Over this gravel I laid another layer of plastic mesh.


That gave me a coarse lower drainage zone while physically separating the gravel from the organic material that would eventually fill most of the tank.


Inside an IBC tank, a vertical mesh-wrapped pipe stands above a gravel layer contained within fabric at the bottom.
A 10–15 cm gravel layer surrounds the mesh-covered drainage pipe before the organic filter material is added.

Building the organic filter bed


For the main biological layer, I wanted a coarse mix with plenty of structure rather than filling the IBC with fine compost.


Most of it came from materials already available locally. I collected coarse leaf litter, sticks, and partly decomposed material from beneath our Mimosa trees. I then bought around 1 m³ (35 ft³) of bark from a local sawmill.


A friend supplied another roughly 1 m³ bulk bag containing aged horse manure mixed with chipped wood.


The manure mixture was already aged by the time I used it.


I combined these materials before loading the tank:


  • coarse Mimosa debris


  • sawmill bark


  • aged horse manure


  • chipped wood


Rather than keeping them as neat layers, I mixed them together and filled the IBC to roughly three-quarters of its total volume.


Red mixing tub holds bark, sticks, and organic material, with a shovel, wheelbarrow, and IBC tank nearby outdoors.
Mixing the coarse organic bedding before loading the IBC, using bark, woody debris, aged horse manure, and chipped wood.

The point of the organic media in a vermifilter is not simply to hold worms. The porous material also provides surface area and habitat for the biological community involved in breaking down incoming organic matter while allowing liquid to move through an aerated bed. Research on vermifiltration shows that earthworms and microorganisms work together within this type of filter environment, while factors such as media choice and hydraulic loading influence how well a system performs.


Adding our worms


Then came the livestock. I did not order a specialist batch of worms for the project. We already had a well-established worm farm living in an old bathtub.


Wheelbarrow filled with dark compost material stands beside a repurposed bathtub containing more organic matter.
A wheelbarrow of red wigglers and worm-rich compost collected from our established bathtub worm farm for the new vermifilter.

I moved roughly one wheelbarrow full of red wigglers together with their worm-rich compost into the prepared IBC.


I cannot tell you their exact species, so I will not pretend otherwise. We know them simply as red wigglers, and they have been doing the dirty work in our ordinary worm farm for years.


For the moment, the IBC is protected from our intense Portuguese summer sun with shade cloth. I have not yet built a more substantial insulated enclosure around it. That makes summer temperature one of the things I will be watching closely once the system receives regular use.


From the Vermifilter to Our Greenfilter Bed


The IBC is only the first physical part of our setup. Liquid leaves through the tank's existing bottom drain outlet. I connected this to 40 mm PVC pipe, using two 90-degree bends before the line connects into a buried 110 mm pipe leading toward the greenfilter area.


Close-up of the IBC outlet connected to black pipework with blue compression fittings and a grey reduction pipe above pipe in a trench.
The IBC bottom outlet connects to the buried outflow line that carries liquid downhill toward the greenfilter bed.

The greenfilter sits approximately 3–4 m (10–13 ft) from the vermicomposting tank.

This downstream area was inspired by the greenfilter or soakaway stage in the system I followed, where liquid leaving the vermifilter is spread through a biologically active area rather than simply leaving the tank at one concentrated point.


Digging the bed


I excavated an area approximately:

2 m × 3 m (6.6 × 9.8 ft)


and at least:

50 cm (20 in) deep


Excavated greenfilter bed with hand tools in the foreground, an IBC tank and gravel trench behind, and a timber-and-stone house uphill.
The hand-dug greenfilter excavation below our granite house, positioned downhill from the future blackwater outlet and vermifilter.

The soil here is exactly what anyone following our granite-house renovation will expect. Dig a hole and eventually Portugal gives you another rock.


Once the excavation was finished, I started filling the bottom with brown organic material and more of the same coarse mixture used in the vermifilter:

Mimosa debris, bark mulch, aged horse manure, and chipped wood.


Wide view of the off-grid vermicomposting system beside a timber-and-stone house, with an IBC tank uphill and a composting bed in the foreground.
The greenfilter bed filled with coarse organic material, with the vermifilter tank downhill from our granite house in the background.

Spreading the flow


Inside the bed, I installed two 40 mm perforated pipes.


Box of plumbing fittings beside grey pipework and a fabric-wrapped perforated tube, arranged near the gravel treatment area.
One of the 40 mm perforated distribution pipes wrapped in leftover drainage textile before installation in the greenfilter bed.

I wrapped both pipes in leftover drainage textile. At their open ends, I simply folded the excess textile together and secured it with zip ties.


IBC tank at the top of a gravel drainage bed feeding grey pipes into a branch-filled vermicomposting soakaway area below.
Two textile-wrapped perforated pipes spread the outflow across as much of our 2 × 3 m greenfilter bed as possible.

The two distribution lines are roughly 1.5 m (5 ft) apart.


Again, I worked with the fittings and pipe lengths I already had rather than designing a perfect-looking diagram and then ordering every fitting from scratch. I arranged the bends to spread the two perforated branches across as much of the 6 m² (65 ft²) greenfilter as practical.


Both sit at approximately a 2-degree fall.


I then covered the pipes with more organic material before returning roughly the final 10 cm (4 in) of excavated soil over the top.


From the surface, most of the wastewater infrastructure has now disappeared.

That was intentional because this area also forms part of a footpath through the property. Nearby are garden beds along with vetiver, a Neem tree, and ornamental plants.


What Is Finished, What Is Not, and What I Will Watch


This is the part of the article where it would be tempting to announce success. I am not going to.


At the moment, we have built the blackwater plumbing, filled and inoculated the vermifilter, connected the drain, constructed the greenfilter, buried the distribution pipes, and protected the IBC with shade cloth.


But the house still needs its final water supply. Our well pump, filtration equipment, and the rest of the house water system need to be connected before the toilet begins operating normally. Until two people are flushing it every day, this remains a finished construction project, not a finished experiment.


And that distinction matters. Research shows that vermifilter performance is affected by operating conditions including organic loading, hydraulic loading, filter media, temperature, and the biological community inside the filter. Full-scale research continues to study how these systems behave across seasons.


So when ours finally goes into full use, I have a list of things I want to observe. I want to see whether the worms remain active through our hot summers and cold winter nights. I want to monitor whether the organic bed stays open or begins compacting. I want to watch how quickly the material level drops and whether extra bark or coarse carbon needs to be added.


I will also watch drainage through the tank, the distribution bed after periods of heavier use, moisture in the greenfilter, any signs of clogging, and what happens to the vegetation around it.


Most importantly, I want time. One good week tells me almost nothing about a wastewater system intended to serve a house for years.


After twelve months, through winter rain and summer heat, we will finally have something useful to talk about.


That is when this story gets Part Two.


Herman's Tough Kraut Fixes: Vermicomposting Toilet System Troubleshooting & FAQ


Because our system has not yet completed its first year under normal household use, this Troubleshooting and FAQ section focuses on construction questions rather than pretending I already have answers to long-term performance problems. These are the practical issues I encountered while turning a drawing and pile of materials into an actual system on our land.


Q: Why did you put the IBC downhill from the house?

A: Gravity. Our IBC sits more than 2 m (6.6 ft) below the house outlets, allowing the 125 mm blackwater pipe to maintain a continuous fall without adding a pump. I used at least a 2-degree slope and gentler 45-degree changes of direction where possible.


Q: Why put gravel and mesh underneath the organic material?

A: I wanted a clear lower drainage zone instead of allowing fine organic material to sit directly against the tank outlet. I used roughly 10–15 cm (4–6 in) of gravel, surrounded the vertical drainage pipe with plastic mesh, then installed another mesh layer before adding the organic bedding.


Q: Why did you mix so many different organic materials?

A: Availability drove much of the decision. Mimosa debris was free on our land, bark was available from a sawmill, and a friend had aged horse manure mixed with chipped wood. I combined them into one coarse mix rather than relying on a single bought material.


Q: Why didn't you identify the worms by species?

A: Because I cannot. They are the red wigglers from our existing bathtub worm farm. Giving them a Latin name without identifying them properly would make the article sound more precise while making it less truthful.


Q: Is the system finished?

A: Construction is largely finished. Testing is not. Normal blackwater loading will begin once the renovated house receives its final pumped and filtered well-water supply. Until then, any claim about long-term performance would be guesswork.

Comments


  • Youtube
  • Facebook
  • Instagram
  • X
  • Pinterest

 

© 2025 - ToughKraut.com

 

bottom of page